Replacement of Lower Level Air Handling Units

A building wide HVAC upgrade began on November 8, 2023 and will continue through the December 2024. 

Mon. 8/5-Wed. 8/7 (starting at 6a) Air handling unit 4 will be replaced but no impact on air flow comfort. Occupants may be impacted by significant noise but mostly on 8/5/24.

Mon. 8/12-Fri. 8/16 (starting at 6a) Air handling unit 3 return fan will be replaced but no impact on air flow comfort. Occupants may be impacted by significant noise but mostly on 8/13/24.     

Fri. 8/23-Sun. 8/25 (starting at 6a) Air handling unit 3 will be replaced and there will be no air flow to Level 2 during this time. Temporary cool units will be put in place but occupants may not be as comfortable as in normal operation. Occupants may be impacted by significant noise but mostly on 8/23/24.       

We appreciate your patience throughout this project!